r4 - 17 Feb 2006 - 11:53:05 - BlazejPietrzakYou are here: TWiki >  PACE Web  >  TopicPERT > PtsFeaturesRequest > PTSMultipleCMAssignment

Multiple Case Manager Assignments

Currently it's only possible to assign a Case Manager per day in the Pert Schedule. We think that it would be helpful if multiple assignments were possible. If such will be the case, it should be possible to specify who the primary CM is.

-- AnaPinto - 01 Jun 2005

This should be given more importance, since the PERT now sometimes has two organisations serving as CMs.

-- SimonLeinen - 06 Dec 2005

Developer comments

Database schema does not have to be modified. PertScheduleChange? class has to be modified to allow multiple assignment. Probably PertSchedule? class also has to be modified to display schedules correctly.

Effort: 1 man/day

-- BartoszBelter - 13 Dec 2005

-- BlazejPietrzak - 13 Dec 2005

Edit | WYSIWYG | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r4 < r3 < r2 < r1 | More topic actions



 