Provide some context for the transition. What is in place now, what is rough timeline for service: for example reach pilot by time a, run pilot for period p and based on results run the service in production by time c. Give some view on what happens with the technical infrastructure through this - i.e the installation will remain ... Example from managed idp transition bellow:
Relation to pilot
...
...
The
...
Accounts created in the pilot installation remain valid until their expiry, or 01 Dec 2018 (whichever comes FIRST; expiry date of intermediate CA).
For the RADIUS authentication of these pilot-phase accounts, there are two options:
- keep the Okeanos-based RADIUS servers running until 01 Dec 2018 (preferred option)
- add the pilot-phase Client Root CA and Client Intermediate CA as trusted on the production servers, so they can authenticate the pilot users.
We have to keep the management UI and the OCSP responder online until 01 Dec 2018 so that activities such as revocation are still possible.
However, pilot-phase IdP administrators should not create new accounts on the pilot system when the production one is available.
The transition generally consist of the following areas of work:
...
Define the people involved:
Teams/people:
- Service Owner and member of the Technical Steering committee: Christos Kanellopoulos
- Member of the Governance engagementSteering Committee: Klaas Wierenga
- Lead Architect and member of the Technical Steering Committee: Leif Johanson
- Development team: Leif Johhanson, Fresia Perez Arriagada, Elena Rakhimova
- Operations team: Erik Bergstörm, Maria Haide (Sunet)
- GEANT T&I operation support/Core team: Nicole HarrisPLM product manager: Not applicable at the moment being this a joint effort between GN4-3/GEANT, Internet2 and the RA21 initiative.
- Test team: ?WP9 - Marcin Wolski (ask what testing can be done)
- IPR: Magdalena Rzaca
- GDPR: Magdalena Rzaca GEANT GDPR team
Status | ||||
---|---|---|---|---|
|
IN PROGRESS
DONE
No | Work item | Responsible | Comment | Status |
---|
Start date
End date
1 | Preparation of documentation | |||
Service Description | -Development team prepares -SO signs off | RA21 Discovery Service Description | ||
Service policy (Terms of use, SLA) | -Development team prepares -SO signs off |
Terms of use |
are out of scope for service delivered by GEANT. It is responisbility of seamlessaccess.org SLA should be defined between seamlesaccess.org and GEANT. | ||
Branding and Visibility | -Development team prepares -SO signs off |
This is probably not relevant to the part of the service delivered by GEANT. It is responisbility of seamlessaccess.org | ||||
Operational Requirements | -Development team prepares -SO signs off | RA21 Discovery Operational Requirements | ||
OLA | -Development team prepares -SO and GEANT T&I operation support/Core team sign off |
RA21 RA21 Discovery Operational Level Agreements (OLA) This is between SUNET and GEANT | ||
Operational documentation | -Development team prepares -SO signs off |
RA21 RA21 Discovery Operational Documentation | ||
Operational processes | -Development team prepares -SO signs off |
Need to define: service order (what happens from point of interest to service availability for a customer) and support process. Marina sent the questionnaire prepared by the Task 4 to Stefan to provide the info and Task 4 can draw the flow charts.
The questionnaire is here.
Not required for production sign-off.
-Development team prepares
-SO signs off
-Development team prepares
-SO signs off
RA21 RA21 Discovery Operational Processes Change management, Incident response, ... | ||||
User documentation | Who is responsible for this? | |||
User support | Who is responsible for this? | |||
GDPR - data inventory, privacy notice, DPA | - |
GDPR team +SO + technical architect -GDPR accountable and |
SO signs off |
The main eduroam privacy notice was updated.
Signed off by the GDPR team on 26th of November 2018. Needs to be published in the eduroam site after the official launch.
DPA will be done together with the eduroam service DPA.
Pen testing done - no critical issues.We should clarify the roles regarding the GDPR. We thing that GEANT and SUNET are data controller, and then probably no DPA is needed. CDNs are data processors. But we would to provide the privacy notice. | ||||
2 | Test and validation | |||
Make a test plan | Development team and Test team prepares |
Testing of the code was done when new version of CAT v2.0 was tested as there use the same code base - no critical issues.
The testing of the UI and usability was also done. There are no bugs, recommendations for UI improvements were implemented by the Development team.
Talk to Marcin and understand the requirements for testing first | ||||
3 | IPR compliance checking | |||
IPR compliance | IPR accountable + SO + technical architect Route the request through GEANT T&I operation support/Core team |
Stefan Winter prepared the IPR request (what are the software components, libraries, tools used) on this page.
Alan confirmed Shaun has approved on 06.11.18
Documentation: eduroam Managed IdP - IPR
To whoom the IPR belongs to ? Needs discussion. | ||||
4 | GDPR compliance checking | GDPR accountable | ||
Data inventory and mapping |
-GDPR team +SO + technical architect -GDPR accountable and SO signs off | |||
Privacy notice and DPA | -GDPR team +SO + technical architect -GDPR accountable and SO signs off |
5 | Operational team establishment | |||
Appoint service owner | WP5 leaders |
It comes under the eduroam service family and existing service manager.
Done. The service owner is responsible for service as delivered via GEANT project. | ||
Define roles, skills, manpower needed | Development team |
We need to check this with what seamlessaccess.org, but if we deliver a service then it is our internal matter. | ||||
Appoint operational team members | Service Owner | Done | ||
6 | Operational team training | |||
Training the operational team | Not needed |
7 | Support team establishment | |||
Establish the support team |
Level 1 done by the GEANT Service Desk, L2 will be over the eduroam-ot, L3 will be via the development team
Note: After PLM enter production gate, SM to notify L1 that the service production startedWe need to understand who provides support | ||||
8 | Support team training | |||
Training of the support team |
We need to understand who provides support | ||||
9 | Deployment in production environment | |||
Monitoring set up | Operations team based on the requirements from the |
technical lead and SO SO signs off when implemented |
Provided by SRCE as part of the eduroam-OT
Back-up and restore | Operations team based on the requirements from the |
technical lead and SO SO signs off when implemented |
VM snapshots are backed up by GEANT IT as defined in the GÉANT PoP Backup policy.
Daily database snapshots are additionally kept at monitor.eduroam.org host.
Perform a smoke test to test the restore process as a whole!! The idea is to take a machine down and ask GEANT IT to restore.
Dick Visser is leading. OCSB machine is the best candidate.
VMs |
Operations team based on the requirements from the |
technical lead and SO SO signs off when implemented |
GEANT IT VMs
Installation of the componentsOne PoP is provided by SUNET. Second PoP will be deployed on AWS, in two different regions. | ||
Deployment | Operations team based on the requirements from the |
technical lead and SO SO signs off when implemented |
Stefan, Tomasz, Maja
SMS service has been ordered and awaiting payment of bank transfer by GÉANT.
CDN | ? |
GEANT T&I operation support/Core team: can organise the root CA creation ceremony, and safe offline storing of the Raspberry PI (in a safe).
Dick Visser will see if there is a safe in the GEANT AMS office. If not, SA2 can purchase one.
In eduroam IdP Operational Processes page there is detail on setting up the CA.
? | |
10 | Service Promotion |
Karl and Justin
Prepare all in the eduroam PR site, but publish when the production gate is passed. Web page draft at https://www.eduroam.org/eduroam-managed-idp/
Marina Adomeit, Miro and Karl prepared the final version only waiting to be published.
Justin
Added to the partner portal. In staging area ready to go live when service goes into production.
Two communications:
First to the participants who joined the infoshare to say that the gate is passed and service is coming
Second upon launch to the GEANT partner list.
Silvie
NA, responsibility of the seamless access | ||||
11 | PLM Documentation | |||
TBD if applicable |
Went into October CONNECT
Miro has let the SG know to expect this. There are meetings in November and December.
CBA update
Costs and funding excel
Roadmap
CBA, costs and funding sheet, and roadmap all updated and put on JRA3 PLM staging site. Alan Lewis has reviewed and is content.
JRA3 PLM Staging Area#emidp-production-gate-documents
Marina Adomeit will, after the PLM gate, move the documentation from the JRA3 PLM staging site to the eduroam wiki pages.