Activities

Pitch

...

New Ideas

Each new idea that was not yet presented to the MIBs will be pitched by the proposer (as part of a MIB meeting).  I.e. formerly Formerly pitched ideas won't be ppresented presented again. In general, a A short pitch consists of a 5 min presentation and 5 min questions.

Discuss

...

Ideas

The

...

MIBs briefly

...

discuss all

...

ideas gathered (MIB meeting)

...

. The discussion focuses on the key aspects, specific questions or new insights

...

, no in depth discussions will be carried out. These discussion should help to choose an idea for the next phase and do not aim to find technical solutions.

Identify Risks

It is checked if there are any risks that might put the implementation of

...

any idea in danger (MIB meeting)

...

.  For example, this concerns Hardware, Software or people not

...

being available. Or the question whether there are parallel projects/tasks that need to be finished at first. Furthermore, GÉANT management decisions or legal conditions must be met

...

as well. If any risk threaten the successful realization of an idea and cannot be solved within a reasonable timeframe the idea may be blocked.

Prioritize Ideas

  1. The MIBs prioritise all not blocked ideas 
    1. The goal is to select four ideas for the next Incubator cycle
    2. Each MIB got four votes, which might be differently weighted
    3. Additionally, two ideas will be selected for the TIM programme with the same procedure
    4. Each member votes independently without knowing the voting results beforehand.
    5. Votes are conducted after the meeting, the MIBs have 7 days to vote

...