Action | Description | Status | Due Date | Assigned to |
---|---|---|---|---|
Service Architecture Documented | Make a reference drawing of service architecture | DONE | Marina, consult with Leif | |
Update the requirements for service operations | To reflect the service architecture that was documented | DONE | Marina, consult with Leif | |
Deploy beta service | IN PROGRESS | End October | Maria, Leif | |
Definition for the hosting environment firewall capabilities | That will be implemented in all different environment. This becomes part of the service definition for baseline operations. | DONE | Leif | |
Prepare the OLA | First draft till 10th October | Marina (consult with Jonny) | ||
Pen testing of the beta service | talk to DFN, end of October, November 2 types of pen testing: no info then full info. First just give the domain. End then we give them the zone file Talk to heather - report of the audit that was alreday done for the privacy audit. WAYF Cloud and P3W Security & Privacy Recommendations | Started talking to DFN cert | Dependent on deploying beta service | Marina via DFN cert (consult Leif, inform Jonny of results) |
Code testing of code that is running as web app | Audit for modern Java Script ? can PSNC do it? Marina to check with Marcin. | Marina via Marcin (consult Leif, inform Jonny of results) | ||
Get budget for the monitoring, and clean up the ops budget | status.io, pingdom.com Marina will prepare the CR from Elena ... use 20 k and move to monitoring and VMs | WP5 leaders approved the 10k budget, need to make the CR | First week October | Marina |
Organise purchase of supporting services | status.io pingdom.com CDN | End November.... | Marina to initiate via Task 3 | |
Configure monitoring | Nagios status.io Pingdom Once licence is available move to the licensed instance | End October (with deployment of beta service) | Leif, Maria, Marina | |
Prepare the financial consumption reporting | when all supporting services are purchased | Marina | ||
Prepare the ops reporting | Marina regular checks with Maria | Marina | ||
Set the public status pages | Leif, Maria, Marina | |||
Check the GDPR | User never touches any of the nodes that are maintained by seamless access.org. The only interaction point is the CDN. Their privacy policy and DPA should be checked!!! Privacy audit ? Bring this up with Heather! Partially already done as audit was done for the infrastructure. external audit on privacy statements - in 2020 as service proves viable | Marina via GEANT project GDPR | ||
Check the IPR? | Leif needs to put the SUNET licence and check the the libraries PSNC should do the audit. Get Magdalena to look to this. Talk to heather about this - who should own the copyright ? Who has the liability for any of this ? | Leif, Marina to connect Leif to Magdalena | ||
Configuration change process | Define the configuration change process. Should be reflected in the OLA. Have in mind other ops regions | Marina (consult with Jonny) | ||
Support process | Define who the support process flow, the actors etc. Should be reflected in the OLA. Have in mind other ops regions. | Marina (consult with Jonny) and take up with Heather | ||
Formulate the L3 support | Leif + certain members from the Technical Sterring group | Marina to take up with Heather | ||
Service operations definition | Prepare a definition of the service ops baseline for additional operators of the service. Security groups and firewall | Marina and Maria, consult with Leif, Tech Steerting group for approval. |